Analisa Harga Satuan Pekerjaan Pondasi Dan Batu
No
|
URAIAN
|
SATUAN
|
KOEF.
|
HARGA SATUAN (Rp)
|
SUB. JUMLAH (Rp)
|
JUMLAH
(Rp)
| |
PEKERJAAN PONDASI & BATU
| |||||||
1.
|
1 m³ Pemasangan pondasi batu belah gabungan 1SP : 3PP
Bahan :
- Batu Belah 15 cm / 20 cm
- PC/Semen
- Pasir pasang
Tenaga Kerja :
- Pekerja
- Tukang Batu
- Kepala Tukang
- Mandor
|
m³
Kg
m³
org/hr
org/hr
org/hr
org/hr
|
1.2
202
0.485
1.5
0.75
0.075
0.075
|
257,000
1,000
265,000
157,643
166,729
182,676
194,274
|
308,400
202,000
128,525
236,464.50
125,046.75
13,700.70
14,570.55
| ||
Jumlah Harga :
|
1,028,707.50
| ||||||
Keuntungan 10% :
| |||||||
Jumlah Harga :
|
1,028,707.50
| ||||||
2.
|
1 m³ Pemasangan pondasi kerikil belah gabungan 1SP : 4PP
Bahan :
- Batu Belah 15 cm / 20 cm
- PC/Semen
- Pasir pasang
Tenaga Kerja :
- Pekerja
- Tukang Batu
- Kepala Tukang
- Mandor
|
m³
Kg
m³
org/hr
org/hr
org/hr
org/hr
|
1.2
163
0.52
1.5
0.75 0.075
0.075
|
257,000
1,000
265,000
157,643
166,729
182,676
194,274
|
308,400
163,000
137,800
236,464.50
125,046.75
13,700.70
14,570.55
| ||
Jumlah Harga :
|
998,982.50
| ||||||
Keuntungan 10% :
| |||||||
Jumlah Harga :
|
998,982.50
| ||||||
3.
|
1 m³ Pemasangan pondasi kerikil belah gabungan 1SP : 5PP
Bahan :
- Batu Belah 15 cm / 20 cm
- PC/Semen
- Pasir pasang
Tenaga Kerja :
- Pekerja
- Tukang Batu
- Kepala Tukang
- Mandor
|
m³
Kg
m³
org/hr
org/hr
org/hr
org/hr
|
1.2
136
0.544
1.5
0.75
0.075
0.075
|
257,000
1,000
265,000
157,643
166,729
182,676
194,274
|
308,400
136.000
144,160
236,464.50
125,046.75
13,700.70
14,570.55
| ||
Jumlah Harga :
|
978,342.50
| ||||||
Keuntungan 10% :
| |||||||
Jumlah Harga :
|
978,342.50
| ||||||
4.
|
1 m³ Pasang Pondasi Batu Belah 1 : 6
Bahan :
- Batu Belah 15 cm / 20 cm
- PC/Semen
- Pasir pasang
Tenaga Kerja :
- Pekerja
- Tukang Batu
- Kepala Tukang
- Mandor
|
m³
Kg
m³
org/hr
org/hr
org/hr
org/hr
|
1.2
117
0.561
1.5
0.75
0.075
0.075
|
257,000
1,000
265,000
157,643
166,729
182,676
194,274
|
308,400
117,000
148,665
236,464.50
125,046.75
13,700.70
14,570.55
| ||
Jumlah Harga :
|
963,847.50
| ||||||
Keuntungan 10% :
| |||||||
Jumlah Harga :
|
963,847.50
| ||||||
5.
|
1 m³ Pasang Pondasi Batu Belah 1 : 8
Bahan :
- Batu Belah 15 cm / 20 cm
- PC/Semen
- Pasir pasang
Tenaga Kerja :
- Pekerja
- Tukang Batu
- Kepala Tukang
- Mandor
|
m³
Kg
m³
org/hr
org/hr
org/hr
org/hr
|
1.2
91
0.584
1.5
0.75
0.075
0.075
|
257,000
1,000
265,000
157,643
166,729
182,676
194,274
|
308,400
91,000
154,760
236,464.50
125,046.75
13,700.70
14,570.55
| ||
Jumlah Harga :
|
943,942.50
| ||||||
Keuntungan 10% :
| |||||||
Jumlah Harga :
|
943,942.50
| ||||||
6.
|
1 m³ Pemasangan kerikil kosong (anstamping)
Bahan :
- Batu Belah 15 cm / 20 cm
- Pasir urug
Tenaga Kerja :
- Pekerja
- Tukang Batu
- Kepala Tukang
- Mandor
|
m³
m³
org/hr
org/hr
org/hr
org/hr
|
1.2
0,432
0.780
0.390 0.039
0.039
|
257,000
210,000
157,643
166,729
182,676
194,274
|
308,400
90,720
122,961.54
65,024.31
7,124.36
7,576.69
| ||
Jumlah Harga :
|
601,806.90
| ||||||
Keuntungan 10% :
| |||||||
Jumlah Harga :
|
601,806.90
| ||||||
7.
|
1 m³ Pasang Bronjong Kawat Batu Kali
Bahan :
- Batu Belah 15 cm / 20 cm
- Kawat bronjong
Tenaga Kerja :
- Pekerja
- Tukang Batu
- Kepala Tukang
- Mandor
|
m³
m2
org/hr
org/hr
org/hr
org/hr
|
1.2
11
0.780 0.390 0.039
0.039
|
257,000
27,000
157,643
166,729
182,676
194,274
|
308,400
297,000
122,961.54
65,024.31
7,124.36
7,576.69
| ||
Jumlah Harga :
|
808,086.90
| ||||||
Keuntungan 10% :
| |||||||
Jumlah Harga :
|
808,086.90
|
Berikut Adalah Analisa Harga Satuan Pekerjaan Pondasi dan Batu,
Semoga bermanfaat bagi yang membaca....
Post a Comment for "Analisa Harga Satuan Pekerjaan Pondasi Dan Batu"