No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,7500 |
81.500,00 |
61.125,00 |
|
Mandor |
OH |
0,0250 |
107.000,00 |
2.675,00 |
|
|
|
JUMLAH TENAGA KERJA |
63.800,00 |
B |
BAHAN |
|
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
|
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
D |
Jumlah (A+B+C) |
|
|
|
63.800,00 |
E |
Overhead & Profit |
|
10% x D |
|
6.380,00 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.1 |
70.180,00 |
A.2.3.1.2 - Penggalian 1 M3 tanah biasa sedalam 2 m |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,900 |
81.500,00 |
73.350,00 |
|
Mandor |
OH |
0,045 |
107.000,00 |
4.815,00 |
|
|
|
JUMLAH TENAGA KERJA |
78.165,00 |
B |
BAHAN |
|
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
|
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
D |
Jumlah (A+B+C) |
|
|
|
78.165,00 |
E |
Overhead & Profit |
|
10% x D |
|
7.816,50 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.2 |
85.981,50 |
A.2.3.1.3 - Menggali 1 M3 tanah biasa sedalam 3 m |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
1,0500 |
81.500,00 |
85.575,00 |
|
Mandor |
OH |
0,0670 |
107.000,00 |
7.169,00 |
|
|
|
JUMLAH TENAGA KERJA |
92.744,00 |
B |
BAHAN |
|
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
|
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
D |
Jumlah (A+B+C) |
|
|
|
92.744,00 |
E |
Overhead & Profit |
|
10% x D |
|
9.274,40 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.3 |
102.018,40 |
A.2.3.1.4 - Menggali 1 M3 tanah keras sedalam 1 m |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
1,0000 |
81.500,00 |
81.500,00 |
|
Mandor |
OH |
0,0320 |
107.000,00 |
3.424,00 |
|
|
|
JUMLAH TENAGA KERJA |
|
84.924,00 |
B |
BAHAN |
|
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
|
|
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
|
D |
Jumlah (A+B+C) |
|
|
|
84.924,00 |
E |
Overhead & Profit |
|
10% x D |
|
8.492,40 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.4 |
93.416,40 |
A.2.3.1.5 - Menggali 1 M3 tanah cadas sedalam 1 m |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
1,500 |
81.500,00 |
122.250,00 |
|
Mandor |
OH |
0,060 |
107.000,00 |
6.420,00 |
|
|
|
JUMLAH TENAGA KERJA |
|
128.670,00 |
B |
BAHAN |
|
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
|
|
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
|
D |
Jumlah (A+B+C) |
|
|
|
128.670,00 |
E |
Overhead & Profit |
|
10% x D |
|
12.867,00 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.5 |
141.537,00 |
A.2.3.1.6 - Menggali 1 M3 tanah lumpur sedalam 1 m |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
1,200 |
81.500,00 |
97.800,00 |
|
Mandor |
OH |
0,045 |
107.000,00 |
4.815,00 |
|
|
|
JUMLAH TENAGA KERJA |
|
102.615,00 |
B |
BAHAN |
|
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
|
|
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
|
D |
Jumlah (A+B+C) |
|
|
|
102.615,00 |
E |
Overhead & Profit |
|
10% x D |
|
10.261,50 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.6 |
112.876,50 |
A.2.3.1.7 - Pengerjaan stripping 1 M2 tanah tebing setinggi 1 meter |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,050 |
81.500,00 |
4.075,00 |
|
Mandor |
OH |
0,005 |
107.000,00 |
535,00 |
|
|
|
JUMLAH TENAGA KERJA |
|
4.610,00 |
B |
BAHAN |
|
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
|
|
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
|
D |
Jumlah (A+B+C) |
|
|
|
4.610,00 |
E |
Overhead & Profit |
|
10% x D |
|
461,00 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.7 |
5.071,00 |
A.2.3.1.8 - Pembuangan 1 M3 tanah sejauh 30 meter |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,330 |
81.500,00 |
26.895,00 |
|
Mandor |
OH |
0,010 |
107.000,00 |
1.070,00 |
|
|
|
JUMLAH TENAGA KERJA |
|
27.965,00 |
B |
BAHAN |
|
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
|
|
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
|
D |
Jumlah (A+B+C) |
|
|
|
27.965,00 |
E |
Overhead & Profit |
|
10% x D |
|
2.796,50 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.8 |
30.761,50 |
A.2.3.1.9 - Pengurugan kembali 1 M3 galian tanah |
Pengurugan kembali 1 M3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,5000 |
81.500,00 |
40.750,00 |
|
Mandor |
OH |
0,0500 |
107.000,00 |
5.350,00 |
|
|
|
JUMLAH TENAGA KERJA |
|
46.100,00 |
B |
BAHAN |
|
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
|
|
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
|
D |
Jumlah (A+B+C) |
|
|
|
46.100,00 |
E |
Overhead & Profit |
|
10% x D |
|
4.610,00 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.9 |
50.710,00 |
A.2.3.1.10 - Pemadatan tanah 1 M3 tanah (per 20 cm) |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,500 |
81.500,00 |
40.750,00 |
|
Mandor |
OH |
0,050 |
107.000,00 |
5.350,00 |
|
|
|
JUMLAH TENAGA KERJA |
|
46.100,00 |
B |
BAHAN |
|
|
|
|
|
|
|
JUMLAH HARGA BAHAN |
|
|
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
|
D |
Jumlah (A+B+C) |
|
|
|
46.100,00 |
E |
Overhead & Profit |
|
10% x D |
|
4.610,00 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.10 |
50.710,00 |
A.2.3.1.11.a - Pengurugan 1 M3 dengan pasir urug |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,3000 |
81.500,00 |
24.450,00 |
|
Mandor |
OH |
0,0100 |
107.000,00 |
1.070,00 |
|
|
|
JUMLAH TENAGA KERJA |
|
25.520,00 |
B |
BAHAN |
|
|
|
|
|
Pasir urug |
|
1,200 |
220.000,00 |
264.000,00 |
|
|
|
JUMLAH HARGA BAHAN |
|
264.000,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
|
D |
Jumlah (A+B+C) |
|
|
|
289.520,00 |
E |
Overhead & Profit |
|
10% x D |
|
28.952,00 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.11.a |
318.472,00 |
A.2.3.1.11b - Pengurugan 1 M3 dengan Tanah Padas |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,3000 |
81.500 |
24.450,00 |
|
Mandor |
OH |
0,0100 |
107.000 |
1.070,00 |
|
|
|
JUMLAH TENAGA KERJA |
|
25.520,00 |
B |
BAHAN |
|
|
|
|
|
Tanah Padas Batu |
|
1,2000 |
120.000,00 |
144.000,00 |
|
|
|
JUMLAH HARGA BAHAN |
|
144.000,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
|
D |
Jumlah (A+B+C) |
|
|
|
169.520,00 |
E |
Overhead & Profit |
|
10% x D |
|
16.952,00 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.11.b |
186.472,00 |
A.2.3.1.12 - Pemasangan 1 M3 lapisan pudel campuran 1KP:3PP:7TL |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,800 |
81.500,00 |
65.200,00 |
|
Tukang |
OH |
0,400 |
96.500,00 |
38.600,00 |
|
Kepala Tukang |
OH |
0,040 |
107.000,00 |
4.280,00 |
|
Mandor |
OH |
0,080 |
107.000,00 |
8.560,00 |
|
|
|
JUMLAH TENAGA KERJA |
|
116.640,00 |
B |
BAHAN |
|
|
|
|
|
Kapur Padam |
M3 |
0,135 |
160.000,00 |
21.600,00 |
|
Pasir Pasang |
M3 |
0,400 |
350.000,00 |
140.000,00 |
|
Tanah Liat |
M3 |
0,948 |
147.000,00 |
139.356,00 |
|
|
|
JUMLAH HARGA BAHAN |
|
300.956,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
|
D |
Jumlah (A+B+C) |
|
|
|
417.596,00 |
E |
Overhead & Profit |
|
10% x D |
|
41.759,60 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.12 |
459.355,60 |
A.2.3.1.13 - Pemasangan 1 M2 lapisan ijuk tebal 10 cm untuk bidang resapan |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,150 |
81.500,00 |
12.225,00 |
|
Mandor |
OH |
0,015 |
107.000,00 |
1.605,00 |
|
|
|
JUMLAH TENAGA KERJA |
|
13.830,00 |
B |
BAHAN |
|
|
|
|
|
Ijuk |
kg |
6,00 |
16.000,00 |
96.000,00 |
|
|
|
JUMLAH HARGA BAHAN |
|
96.000,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
|
D |
Jumlah (A+B+C) |
|
|
|
109.830,00 |
E |
Overhead & Profit |
|
10% x D |
|
10.983,00 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.13 |
120.813,00 |
A.2.3.1.15 - Pengurugan 1 M3 sirtu padat |
No |
Uraian |
Satuan |
Koefisien |
Harga Satuan |
Jumlah Harga |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,2500 |
81.500,00 |
20.375,00 |
|
Mandor |
OH |
0,0250 |
107.000,00 |
2.675,00 |
|
|
|
JUMLAH TENAGA KERJA |
|
23.050,00 |
B |
BAHAN |
|
|
|
|
|
Sirtu |
M3 |
1,2000 |
184.000,00 |
220.800,00 |
|
|
|
JUMLAH HARGA BAHAN |
|
220.800,00 |
C |
PERALATAN |
|
|
|
|
|
|
|
JUMLAH HARGA ALAT |
|
|
D |
Jumlah (A+B+C) |
|
|
|
243.850,00 |
E |
Overhead & Profit |
|
10% x D |
|
24.385,00 |
F |
Harga Satuan Pekerjaan (D+E) |
|
|
A.2.3.1.15 |
268.235,00 |