Skip to content
A.2.2.1.7.a - Pembuatan 1 M2 gudang semen dan peralatan
A.2.2.1.7.a - Pembuatan 1 M2 gudang semen dan peralatan |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
1,0000 |
81.500,00 |
81.500,00 |
|
Tukang Kayu |
OH |
2,0000 |
96.500,00 |
193.000,00 |
|
Kepala Tukang |
OH |
0,2000 |
107.000,00 |
21.400,00 |
|
Mandor |
OH |
0,0500 |
107.000,00 |
5.350,00 |
|
|
|
JUMLAH HARGA TENAGA |
301.250,00 |
B |
BAHAN |
|
|
|
|
|
Dolken bambu |
Batang |
1,7000 |
25.000,00 |
42.500,00 |
|
Kayu |
m |
0,2100 |
7.500.000,00 |
1.575.000,00 |
|
Paku biasa |
Kg |
0,3000 |
23.000,00 |
6.900,00 |
|
Semen Portland |
Kg |
10,5000 |
1.250,00 |
13.125,00 |
|
Pasir beton |
M3 |
0,0300 |
350.000,00 |
10.500,00 |
|
Koral beton |
M3 |
0,0500 |
215.000,00 |
10.750,00 |
|
Seng gelombang |
Lbr |
1,5000 |
54.000,00 |
81.000,00 |
|
Seng plat |
Lbr |
0,2500 |
28.000,00 |
7.000,00 |
|
|
|
JUMLAH HARGA BAHAN |
1.746.775,00 |
C |
ALAT |
|
|
|
|
|
- |
|
|
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
2.048.025,00 |
E |
Overhead & Profit |
10% x D |
|
|
204.802,50 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
2.252.827,50 |