NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0250 81.500,00 2.037,50
Tukang Besi OH 0,0250 96.500,00 2.412,50
Kepala Tukang OH 0,0250 107.000,00 2.675,00
Mandor OH 0,0010 107.000,00 107,00
JUMLAH HARGA TENAGA 7.232,00
B BAHAN
1. Jaring kawat baja   dilas Kg 10,2000 12.000,00 122.400,00
2. Kawat beton Kg 0,0500 23.500,00 1.175,00
JUMLAH HARGA BAHAN 123.575,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 130.807,00
E Overhead & Profit 10% x D 13.080,70
F HARGA SATUAN   PEKERJAAN ( D + E ) 143.887,70