A.4.1.1.21 - Pemasangan 1 M2 bekisting untuk sloof
A.4.1.1.21 - Pemasangan 1 M2 bekisting untuk sloof |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,5200 |
81.500,00 |
42.380,00 |
|
Tukang Kayu |
OH |
0,2600 |
96.500,00 |
25.090,00 |
|
Kepala Tukang |
OH |
0,0260 |
107.000,00 |
2.782,00 |
|
Mandor |
OH |
0,0260 |
107.000,00 |
2.782,00 |
|
|
|
JUMLAH HARGA TENAGA |
73.034,00 |
B |
BAHAN |
|
|
|
|
|
Kayu kelas III |
M3 |
0,0450 |
3.500.000,00 |
157.500,00 |
|
Paku 5 cm – 10 cm |
Kg |
0,3000 |
23.000,00 |
6.900,00 |
|
Minyak bekisting |
Liter |
0,1000 |
5.150,00 |
515,00 |
|
|
|
JUMLAH HARGA BAHAN |
164.915,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
237.949,00 |
E |
Overhead & Profit |
10% x D |
|
|
23.794,90 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
261.743,90 |