A.4.1.1.27a - Pemasangan 1 M2 jembatan untuk pengecoran beton
A.4.1.1.27a - Pemasangan 1 M2 jembatan untuk pengecoran beton |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,1500 |
81.500,00 |
12.225,00 |
|
Tukang Kayu |
OH |
0,0500 |
96.500,00 |
4.825,00 |
|
Kepala Tukang |
OH |
0,0050 |
107.000,00 |
535,00 |
|
Mandor |
OH |
0,0080 |
107.000,00 |
856,00 |
|
|
|
JUMLAH HARGA TENAGA |
18.441,00 |
B |
BAHAN |
|
|
|
|
|
Kayu kelas III (papan) |
M3 |
0,0264 |
3.500.000,00 |
92.400,00 |
|
Paku 5 cm – 12 cm |
Kg |
0,6000 |
23.000,00 |
13.800,00 |
|
Dolken Bambu |
Batang |
0,5000 |
25.000,00 |
12.500,00 |
|
|
|
JUMLAH HARGA BAHAN |
118.700,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
137.141,00 |
E |
Overhead & Profit |
10% x D |
|
|
13.714,10 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
150.855,10 |