A.4.1.1.30a - Membuat 1 M3 kolom beton bertulang (300 Kg besi + bekisting)

A.4.1.1.30a - Membuat 1 M3 kolom beton bertulang (300 Kg besi +   bekisting)
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 7,0500 81.500,00 574.575,00
Tukang batu OH 0,2750 96.500,00 26.537,50
Tukang kayu OH 1,6500 96.500,00 159.225,00
Tukang besi OH 2,1000 96.500,00 202.650,00
Kepala tukang OH 0,4030 107.000,00 43.121,00
Mandor OH 0,3530 107.000,00 37.771,00
JUMLAH HARGA TENAGA 1.043.879,50
B BAHAN
Kayu kelas III M3 0,4000 3.500.000,00 1.400.000,00
Paku 5 cm – 12cm Kg 4,0000 23.000,00 92.000,00
Minyak bekisting Liter 2,0000 5.150,00 10.300,00
Besi beton polos Kg 315,0000 10.100,00 3.181.500,00
Kawat beton Kg 4,5000 23.500,00 105.750,00
Semen Portland Kg 336,0000 1.250,00 420.000,00
Pasir Beton M3 0,5400 350.000,00 189.000,00
Kerikil M3 0,8100 364.000,00 294.840,00
Kayu kelas II balok M3 0,1500 4.500.000,00 675.000,00
Plywood 9 mm Lbr 3,5000 125.000,00 437.500,00
Dolken Bambu Batang 20,0000 25.000,00 500.000,00
JUMLAH HARGA BAHAN 7.305.890,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 8.349.769,50
E Overhead & Profit 10% x D 834.976,95
F HARGA SATUAN   PEKERJAAN ( D + E ) 9.184.746,45