NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 5,6500 81.500,00 460.475,00
Tukang batu OH 0,2750 96.500,00 26.537,50
Tukang kayu OH 1,5600 96.500,00 150.540,00
Tukang besi OH 1,4000 96.500,00 135.100,00
Kepala tukang OH 0,3230 107.000,00 34.561,00
Mandor OH 0,2830 107.000,00 30.281,00
JUMLAH HARGA TENAGA 837.494,50
B BAHAN
Kayu kelas III M3 0,2500 3.500.000,00 875.000,00
Paku 5 cm – 12 cm Kg 3,0000 23.000,00 69.000,00
Minyak bekisting Liter 1,2000 5.150,00 6.180,00
Besi beton polos Kg 210,0000 10.100,00 2.121.000,00
Kawat beton Kg 3,0000 23.500,00 70.500,00
Semen Portland Kg 336,0000 1.250,00 420.000,00
Pasir Beton M3 0,5400 350.000,00 189.000,00
Kerikil M3 0,8100 364.000,00 294.840,00
Kayu kelas II balok M3 0,1050 4.500.000,00 472.500,00
Plywood 9 mm Lembar 2,5000 125.000,00 312.500,00
Dolken Bambu Batang 14,0000 25.000,00 350.000,00
JUMLAH HARGA BAHAN 5.180.520,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 6.018.014,50
E Overhead & Profit 10% x D 601.801,45
F HARGA SATUAN   PEKERJAAN ( D + E ) 6.619.815,95