NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,2970 81.500,00 24.205,50
Tukang batu OH 0,0330 96.500,00 3.184,50
Tukang kayu OH 0,0330 96.500,00 3.184,50
Tukang besi OH 0,0330 96.500,00 3.184,50
Kepala tukang OH 0,0100 107.000,00 1.070,00
Mandor OH 0,0150 107.000,00 1.605,00
JUMLAH HARGA TENAGA 36.434,00
B BAHAN
Kayu kelas III M3 0,0030 3.500.000,00 10.500,00
Paku 5 cm – 12 cm Kg 0,0200 23.000,00 460,00
Besi beton polos Kg 3,6000 10.100,00 36.360,00
Kawat beton Kg 0,0500 23.500,00 1.175,00
Semen Portland Kg 5,5000 1.250,00 6.875,00
Pasir Beton M3 0,0090 350.000,00 3.150,00
Kerikil M3 0,0150 364.000,00 5.460,00
JUMLAH HARGA BAHAN 63.980,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 100.414,00
E Overhead & Profit 10% x D 10.041,40
F HARGA SATUAN   PEKERJAAN ( D + E ) 110.455,40