A.4.2.1.1 - Pemasangan 1 Kg besi profil
A.4.2.1.1 - Pemasangan 1 Kg besi profil | |||||
---|---|---|---|---|---|
NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
A | TENAGA | ||||
Pekerja | OH | 0,0600 | 81.500,00 | 4.890,00 | |
TukangKonstruksiLas | OH | 0,0600 | 96.500,00 | 5.790,00 | |
Kepala tukang | OH | 0,0060 | 107.000,00 | 642,00 | |
Mandor | OH | 0,0030 | 107.000,00 | 321,00 | |
JUMLAH HARGA TENAGA | 11.643,00 | ||||
B | BAHAN | ||||
Besi Profil | Kg | 1,1500 | 10.500,00 | 12.075,00 | |
JUMLAH HARGA BAHAN | 12.075,00 | ||||
C | ALAT | ||||
- | - | - | - | - | |
JUMLAH HARGA ALAT | - | ||||
D | Jumlah | (A+B+C) | 23.718,00 | ||
E | Overhead & Profit | 10% x D | 2.371,80 | ||
F | HARGA SATUAN PEKERJAAN | ( D + E ) | 26.089,80 |