Skip to content Skip to sidebar Skip to footer

A.4.2.1.11d - Pemasangan 1 M' kusen pintu alluminium Silver 4"

A.4.2.1.11d - Pemasangan 1 M' kusen pintu alluminium Silver   4"
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0430 81.500,00 3.504,50
TukangAlumuniumKhusus OH 0,0430 96.500,00 4.149,50
Kepala tukang OH 0,0043 107.000,00 460,10
Mandor OH 0,0021 107.000,00 224,70
JUMLAH HARGA TENAGA 8.338,80
B BAHAN
Profil alluminium silver 4" M' 1,1000 85.000,00 93.500,00
Skrup fixer Buah 2,0000 1.500,00 3.000,00
Sealant Tube 0,0600 12.500,00 750,00
JUMLAH HARGA BAHAN 97.250,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 105.588,80
E Overhead & Profit 10% x D 10.558,88
F HARGA SATUAN   PEKERJAAN ( D + E ) 116.147,68