NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 1,6700 81.500,00 136.105,00
Tukang Las OH 1,6700 96.500,00 161.155,00
Kepala tukang OH 0,1670 107.000,00 17.869,00
Mandor OH 0,0830 107.000,00 8.881,00
JUMLAH HARGA TENAGA 324.010,00
B BAHAN
Besi strip Kg 6,1770 15.200,00 93.890,40
Pengelasan Cm 27,0800 7.836,18 212.203,75
JUMLAH HARGA BAHAN 306.094,15
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 630.104,15
E Overhead & Profit 10% x D 63.010,42
F HARGA SATUAN   PEKERJAAN ( D + E ) 693.114,57