A.4.2.1.17 - Pemasangan 1 M2 jendela nako & tralis
A.4.2.1.17 - Pemasangan 1 M2 jendela nako & tralis | |||||
---|---|---|---|---|---|
NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
A | TENAGA | ||||
Pekerja | OH | 0,2000 | 81.500,00 | 16.300,00 | |
Tukang | OH | 0,2000 | 96.500,00 | 19.300,00 | |
Kepala tukang | OH | 0,0200 | 107.000,00 | 2.140,00 | |
Mandor | OH | 0,0010 | 107.000,00 | 107,00 | |
JUMLAH HARGA TENAGA | 37.847,00 | ||||
B | BAHAN | ||||
Jendela(rangka +nakokaca 5 mm) | M2 | 1,1000 | 16.000,00 | 17.600,00 | |
Paku skrup 1 cm – 2,5 cm | Buah | 10,0000 | 6.250,00 | 62.500,00 | |
Besi strip | M' | 7,0000 | 15.200,00 | 106.400,00 | |
JUMLAH HARGA BAHAN | 106.400,00 | ||||
C | ALAT | ||||
- | - | - | - | - | |
JUMLAH HARGA ALAT | - | ||||
D | Jumlah | (A+B+C) | 144.247,00 | ||
E | Overhead & Profit | 10% x D | 14.424,70 | ||
F | HARGA SATUAN PEKERJAAN | ( D + E ) | 158.671,70 |