A.4.2.1.18 - Pemasangan 1 M' talang datar/ jurai seng bjls 28 lebar 90 cm

A.4.2.1.18 - Pemasangan 1 M' talang datar/ jurai seng bjls 28 lebar 90 cm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,2000 81.500,00 16.300,00
Tukang OH 0,2000 96.500,00 19.300,00
Kepala tukang OH 0,0200 107.000,00 2.140,00
Mandor OH 0,0010 107.000,00 107,00
JUMLAH HARGA TENAGA 37.847,00
B BAHAN
Seng plat M' 1,0500 41.000,00 43.050,00
Paku 1 cm - 2,5 cm Kg 0,0150 23.000,00 345,00
Papan kayu kelas II M3 0,0190 9.500.000,00 180.500,00
223.895,00
JUMLAH HARGA BAHAN
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 261.742,00
E Overhead & Profit 10% x D 26.174,20
F HARGA SATUAN   PEKERJAAN ( D + E ) 287.916,20