A.4.2.1.19 - Pemasangan 1 M ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm
A.4.2.1.19 - Pemasangan 1 M ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,1500 |
81.500,00 |
12.225,00 |
|
Tukang |
OH |
0,3000 |
96.500,00 |
28.950,00 |
|
Kepala tukang |
OH |
0,0300 |
107.000,00 |
3.210,00 |
|
Mandor |
OH |
0,0080 |
107.000,00 |
856,00 |
|
|
|
JUMLAH HARGA TENAGA |
45.241,00 |
B |
BAHAN |
|
|
|
|
|
Seng plat |
M' |
1,0500 |
41.000,00 |
43.050,00 |
|
Paku 1 cm – 2,5 cm |
Kg |
0,0100 |
23.000,00 |
230,00 |
|
Besi strip |
Kg |
0,5000 |
15.200,00 |
7.600,00 |
|
|
|
JUMLAH HARGA BAHAN |
50.880,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
96.121,00 |
E |
Overhead & Profit |
10% x D |
|
|
9.612,10 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
105.733,10 |