A.4.2.1.19 - Pemasangan 1 M ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm

A.4.2.1.19 - Pemasangan 1 M ½ lingkaran D-15 cm, seng plat bjls   30 lebar 45 cm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,1500 81.500,00 12.225,00
Tukang OH 0,3000 96.500,00 28.950,00
Kepala tukang OH 0,0300 107.000,00 3.210,00
Mandor OH 0,0080 107.000,00 856,00
JUMLAH HARGA TENAGA 45.241,00
B BAHAN
Seng plat M' 1,0500 41.000,00 43.050,00
Paku 1 cm – 2,5 cm Kg 0,0100 23.000,00 230,00
Besi strip Kg 0,5000 15.200,00 7.600,00
JUMLAH HARGA BAHAN 50.880,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 96.121,00
E Overhead & Profit 10% x D 9.612,10
F HARGA SATUAN   PEKERJAAN ( D + E ) 105.733,10