A.4.2.1.19 - Pemasangan 1 M ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm
A.4.2.1.19 - Pemasangan 1 M ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm | |||||
---|---|---|---|---|---|
NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
A | TENAGA | ||||
Pekerja | OH | 0,1500 | 81.500,00 | 12.225,00 | |
Tukang | OH | 0,3000 | 96.500,00 | 28.950,00 | |
Kepala tukang | OH | 0,0300 | 107.000,00 | 3.210,00 | |
Mandor | OH | 0,0080 | 107.000,00 | 856,00 | |
JUMLAH HARGA TENAGA | 45.241,00 | ||||
B | BAHAN | ||||
Seng plat | M' | 1,0500 | 41.000,00 | 43.050,00 | |
Paku 1 cm – 2,5 cm | Kg | 0,0100 | 23.000,00 | 230,00 | |
Besi strip | Kg | 0,5000 | 15.200,00 | 7.600,00 | |
JUMLAH HARGA BAHAN | 50.880,00 | ||||
C | ALAT | ||||
- | - | - | - | - | |
JUMLAH HARGA ALAT | - | ||||
D | Jumlah | (A+B+C) | 96.121,00 | ||
E | Overhead & Profit | 10% x D | 9.612,10 | ||
F | HARGA SATUAN PEKERJAAN | ( D + E ) | 105.733,10 |