A.4.2.1.5 - Pengerjaan 10 Cm pengelasan dengan las listrik
A.4.2.1.5 - Pengerjaan 10 Cm pengelasan dengan las listrik |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,0400 |
81.500,00 |
3.260,00 |
|
TukangKonstruksiBesi |
OH |
0,0200 |
96.500,00 |
1.930,00 |
|
Kepala tukang |
OH |
0,0020 |
107.000,00 |
214,00 |
|
Mandor |
OH |
0,0020 |
107.000,00 |
214,00 |
|
|
|
JUMLAH HARGA TENAGA |
5.618,00 |
B |
BAHAN |
|
|
|
|
|
Kawat las listrik |
Kg |
0,4000 |
36.150,00 |
14.460,00 |
|
Solar |
Liter |
0,3000 |
10.200,00 |
3.060,00 |
|
Minyak pelumas |
Liter |
0,0400 |
55.000,00 |
2.200,00 |
|
|
|
JUMLAH HARGA BAHAN |
19.720,00 |
C |
ALAT |
|
|
|
|
|
Sewa alat |
Jam |
0,1700 |
270.000,00 |
45.900,00 |
|
|
|
JUMLAH HARGA ALAT |
45.900,00 |
D |
Jumlah |
(A+B+C) |
|
|
71.238,00 |
E |
Overhead & Profit |
10% x D |
|
|
7.123,80 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
78.361,80 |