A.4.2.1.7 - Pemasangan 1 M2 pintu rolling door besi
A.4.2.1.7 - Pemasangan 1 M2 pintu rolling door besi |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
1,2000 |
81.500,00 |
97.800,00 |
|
Tukang Las Biasa |
OH |
1,2000 |
96.500,00 |
115.800,00 |
|
Kepala tukang |
OH |
0,1200 |
107.000,00 |
12.840,00 |
|
Mandor |
OH |
0,0060 |
107.000,00 |
642,00 |
|
|
|
JUMLAH HARGA TENAGA |
227.082,00 |
B |
BAHAN |
|
|
|
|
|
Pintu gulung besi |
M2 |
1,0000 |
475.000,00 |
475.000,00 |
|
|
|
JUMLAH HARGA BAHAN |
475.000,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
702.082,00 |
E |
Overhead & Profit |
10% x D |
|
|
70.208,20 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
772.290,20 |