A.4.4.1.11 - Pemasangan 1M2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP : 6PP

A.4.4.1.11 - Pemasangan 1M2 dinding bata   merah (5x11x22)cm tebal ½ batu campuran 1SP : 6PP
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,3000 81.500,00 24.450,00
Tukang Batu OH 0,1000 96.500,00 9.650,00
Kepala Tukang OH 0,0100 107.000,00 1.070,00
Mandor OH 0,0150 107.000,00 1.605,00
JUMLAH HARGA TENAGA 36.775,00
B BAHAN
Bata merah Bh 70,0000 600,00 42.000,00
Semen Portland Kg 8,3200 1.250,00 10.400,00
Pasir Pasang M3 0,0490 350.000,00 17.150,00
JUMLAH HARGA BAHAN 69.550,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 106.325,00
E Overhead & Profit 10% x D 10.632,50
F HARGA SATUAN   PEKERJAAN ( D + E )    116.957,50