A.4.4.1.4 - Pemasangan 1M2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5 PP
A.4.4.1.4 - Pemasangan 1M2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5 PP | |||||
---|---|---|---|---|---|
NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
A | TENAGA | ||||
Pekerja | OH | 0,6000 | 81.500,00 | 48.900,00 | |
Tukang Batu | OH | 0,2000 | 96.500,00 | 19.300,00 | |
Kepala Tukang | OH | 0,0200 | 107.000,00 | 2.140,00 | |
Mandor | OH | 0,0300 | 107.000,00 | 3.210,00 | |
JUMLAH HARGA TENAGA | 73.550,00 | ||||
B | BAHAN | ||||
Bata merah | Bh | 140,0000 | 600,00 | 84.000,00 | |
Semen Portlan | Kg | 22,2000 | 1.250,00 | 27.750,00 | |
Pasir Pasang | M3 | 0,1020 | 350.000,00 | 35.700,00 | |
JUMLAH HARGA BAHAN | 147.450,00 | ||||
C | ALAT | ||||
- | - | - | - | - | |
JUMLAH HARGA ALAT | - | ||||
D | Jumlah | (A+B+C) | 221.000,00 | ||
E | Overhead & Profit | 10% x D | 22.100,00 | ||
F | HARGA SATUAN PEKERJAAN | ( D + E ) | 243.100,00 |
Post a Comment for "A.4.4.1.4 - Pemasangan 1M2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 5 PP"