NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,6000 81.500,00 48.900,00
Tukang Batu OH 0,2000 96.500,00 19.300,00
Kepala Tukang OH 0,0200 107.000,00 2.140,00
Mandor OH 0,0300 107.000,00 3.210,00
JUMLAH HARGA TENAGA 73.550,00
B BAHAN
Bata merah Bh 140,0000 600,00 84.000,00
Semen Portlan Kg 18,5000 1.250,00 23.125,00
Pasir Pasang M3 0,1220 350.000,00 42.700,00
JUMLAH HARGA BAHAN 149.825,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 223.375,00
E Overhead & Profit 10% x D 22.337,50
F HARGA SATUAN   PEKERJAAN ( D + E )    245.712,50