A.4.4.1.6 - Pemasangan 1M2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3KP : 10PP

A.4.4.1.6 - Pemasangan 1M2 dinding bata merah   (5x11x22) cm tebal 1 batu campuran 1SP : 3KP : 10PP
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,60000 81.500,00 48.900,00
Tukang Batu OH 0,20000 96.500,00 19.300,00
Kepala Tukang OH 0,02000 107.000,00 2.140,00
Mandor OH 0,03000 107.000,00 3.210,00
JUMLAH HARGA TENAGA 73.550,00
B BAHAN
Bata merah Bh 140,00000 600,00 84.000,00
Semen Portlan Kg 10,08000 1.250,00 12.600,00
Kapur Padam M3 0,02750 160.000,00 4.400,00
Pasir Pasang M3 0,09250 350.000,00 32.375,00
JUMLAH HARGA BAHAN 133.375,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 206.925,00
E Overhead & Profit 10% x D 20.692,50
F HARGA SATUAN   PEKERJAAN ( D + E )    227.617,50