A.4.4.1.9 - Pemasangan 1M2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4PP

A.4.4.1.9 - Pemasangan 1M2 dinding bata merah   (5x11x22) cm tebal ½ batu campuran 1SP :4PP
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,3000 81.500,00 24.450,00
Tukang Batu OH 0,1000 96.500,00 9.650,00
Kepala Tukang OH 0,0100 107.000,00 1.070,00
Mandor OH 0,0150 107.000,00 1.605,00
JUMLAH HARGA TENAGA 36.775,00
B BAHAN
Bata merah Bh 70,0000 600,00 42.000,00
Semen Portlan Kg 11,5000 1.250,00 14.375,00
Pasir Pasang M3 0,0430 350.000,00 15.050,00
JUMLAH HARGA BAHAN 71.425,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 108.200,00
E Overhead & Profit 10% x D 10.820,00
F HARGA SATUAN   PEKERJAAN ( D + E )    119.020,00