A.4.4.2.11 - Pemasangan 1 M2 plesteran 1SM : 1KP : 1PP tebal 15 mm

A.4.4.2.11 - Pemasangan 1 M2 plesteran 1SM : 1KP : 1PP tebal 15   mm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,3600 81.500,00 29.340,00
Tukang Batu OH 0,1200 96.500,00 11.580,00
Kepala Tukang OH 0,0120 107.000,00 1.284,00
Mandor OH 0,0180 107.000,00 1.926,00
JUMLAH HARGA TENAGA 44.130,00
B BAHAN
Semen Merah M3 0,0090 19.800,00 178,20
Kapur Padam M3 0,0090 160.000,00 1.440,00
Pasir Pasang M3 0,0090 350.000,00 3.150,00
JUMLAH HARGA BAHAN 4.768,20
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 48.898,20
E Overhead & Profit 10% x D 4.889,82
F HARGA SATUAN   PEKERJAAN ( D + E )    53.788,02