A.4.4.2.13 - Pemasangan 1 M2 plesteran 1SP : 1PP tebal 20 mm

A.4.4.2.13 - Pemasangan 1 M2 plesteran 1SP : 1PP tebal 20 mm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,4000 81.500,00 32.600,00
Tukang Batu OH 0,2000 96.500,00 19.300,00
Kepala Tukang OH 0,0200 107.000,00 2.140,00
Mandor OH 0,0220 107.000,00 2.354,00
JUMLAH HARGA TENAGA 56.394,00
B BAHAN
Portland Cement Kg 13,6320 1.250,00 17.040,00
Pasir Pasang M3 0,0270 350.000,00 9.450,00
JUMLAH HARGA BAHAN 26.490,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 82.884,00
E Overhead & Profit 10% x D 8.288,40
F HARGA SATUAN   PEKERJAAN ( D + E )    91.172,40