A.4.4.2.14 - Pemasangan 1 M2 plesteran 1SP : 3PP tebal 20 mm

A.4.4.2.14 - Pemasangan 1 M2 plesteran 1SP : 3PP tebal 20 mm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,2600 81.500,00 21.190,00
Tukang Batu OH 0,2000 96.500,00 19.300,00
Kepala Tukang OH 0,0200 107.000,00 2.140,00
Mandor OH 0,0130 107.000,00 1.391,00
JUMLAH HARGA TENAGA 44.021,00
B BAHAN
Portland Cement Kg 10,3680 1.250,00 12.960,00
Pasir Pasang M3 0,0310 350.000,00 10.850,00
JUMLAH HARGA BAHAN 23.810,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 67.831,00
E Overhead & Profit 10% x D 6.783,10
F HARGA SATUAN   PEKERJAAN ( D + E )    74.614,10