A.4.4.2.15 - Pemasangan 1 M2 plesteran 1SP : 4PP tebal 20 mm

A.4.4.2.15 - Pemasangan 1 M2 plesteran 1SP : 4PP tebal 20 mm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,4000 81.500,00 32.600,00
Tukang Batu OH 0,2000 96.500,00 19.300,00
Kepala Tukang OH 0,0200 107.000,00 2.140,00
Mandor OH 0,0220 107.000,00 2.354,00
JUMLAH HARGA TENAGA 56.394,00
B BAHAN
Portland Cement Kg 8,3200 1.250,00 10.400,00
Pasir Pasang M3 0,0320 350.000,00 11.200,00
JUMLAH HARGA BAHAN 21.600,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 77.994,00
E Overhead & Profit 10% x D 7.799,40
F HARGA SATUAN   PEKERJAAN ( D + E )    85.793,40