A.4.4.2.20. Pemasangan 1 m’ plesteran skoning 1SP : 3PP lebar 10 cm

A.4.4.2.20. Pemasangan 1 m’ plesteran skoning 1SP : 3PP lebar 10   cm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0800 81.500,00 6.520,00
Tukang Batu OH 0,4000 96.500,00 38.600,00
Kepala Tukang OH 0,0400 107.000,00 4.280,00
Mandor OH 0,0040 107.000,00 428,00
JUMLAH HARGA TENAGA 49.828,00
B BAHAN
Portland Cement Kg 0,5000 1.250,00 625,00
Pasir Pasang M3 0,0130 350.000,00 4.550,00
JUMLAH HARGA BAHAN 5.175,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 55.003,00
E Overhead & Profit 10% x D 5.500,30
F HARGA SATUAN   PEKERJAAN ( D + E )    60.503,30