A.4.4.2.25 - Pemasangan 1 M2 finishing siar pasangan conblock ekspose

A.4.4.2.25 - Pemasangan 1 M2 finishing siar pasangan conblock   ekspose
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0700 81.500,00 5.705,00
Tukang Batu OH 0,0350 96.500,00 3.377,50
Kepala Tukang OH 0,0040 107.000,00 428,00
Mandor OH 0,0040 107.000,00 428,00
JUMLAH HARGA TENAGA 9.938,50
B BAHAN
Portland Cement Kg 1,6000 1.250,00 2.000,00
JUMLAH HARGA BAHAN 2.000,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 11.938,50
E Overhead & Profit 10% x D 1.193,85
F HARGA SATUAN   PEKERJAAN ( D + E )    13.132,35