NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,3000 81.500,00 24.450,00
Tukang Batu OH 0,1500 96.500,00 14.475,00
Kepala Tukang OH 0,0150 107.000,00 1.605,00
Mandor OH 0,0150 107.000,00 1.605,00
JUMLAH HARGA TENAGA 42.135,00
B BAHAN
Portland Cement Kg 6,3400 1.250,00 7.925,00
Pasir Pasang M3 0,0120 350.000,00 4.200,00
JUMLAH HARGA BAHAN 12.125,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 54.260,00
E Overhead & Profit 10% x D 5.426,00
F HARGA SATUAN   PEKERJAAN ( D + E )    59.686,00