Skip to content Skip to sidebar Skip to footer

A.4.4.2.5 - Pemasangan 1 M2 plesteran 1SP : 5PP tebal 15 mm

A.4.4.2.5 - Pemasangan 1 M2 plesteran 1SP : 5PP tebal 15 mm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,3000 81.500,00 24.450,00
Tukang Batu OH 0,1500 96.500,00 14.475,00
Kepala Tukang OH 0,0150 107.000,00 1.605,00
Mandor OH 0,0150 107.000,00 1.605,00
JUMLAH HARGA TENAGA 42.135,00
B BAHAN
Portland Cement Kg 5,1840 1.250,00 6.480,00
Pasir Pasang M3 0,0260 350.000,00 9.100,00
JUMLAH HARGA BAHAN 15.580,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 57.715,00
E Overhead & Profit 10% x D 5.771,50
F HARGA SATUAN   PEKERJAAN ( D + E )    63.486,50



======= ARTIKEL TERKAIT =======



Post a Comment for "A.4.4.2.5 - Pemasangan 1 M2 plesteran 1SP : 5PP tebal 15 mm"