A.4.4.2.9 - Pemasangan 1 M2 plesteran 1SP : 1/2KP : 3PP tebal 15 mm

A.4.4.2.9 - Pemasangan 1 M2 plesteran 1SP : 1/2KP : 3PP tebal 15   mm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,3600 81.500,00 29.340,00
Tukang Batu OH 0,1200 96.500,00 11.580,00
Kepala Tukang OH 0,0120 107.000,00 1.284,00
Mandor OH 0,0180 107.000,00 1.926,00
JUMLAH HARGA TENAGA 44.130,00
B BAHAN
Portland Cement Kg 5,7600 1.250,00 7.200,00
Kapur Padam M3 0,0030 160.000,00 480,00
Pasir Pasang M3 0,0130 350.000,00 4.550,00
JUMLAH HARGA BAHAN 12.230,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 56.360,00
E Overhead & Profit 10% x D 5.636,00
F HARGA SATUAN   PEKERJAAN ( D + E )    61.996,00