Skip to content
A.4.4.3.55a - Pemasangan 1 M2 dinding marmer 60cm x 60cm
A.4.4.3.55a - Pemasangan 1 M2 dinding marmer 60cm x 60cm |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
1,3000 |
81.500,00 |
105.950,00 |
|
Tukang Batu |
OH |
0,6500 |
96.500,00 |
62.725,00 |
|
Kepala tukang |
OH |
0,0650 |
107.000,00 |
6.955,00 |
|
Mandor |
OH |
0,0650 |
107.000,00 |
6.955,00 |
|
|
|
JUMLAH HARGA TENAGA |
182.585,00 |
B |
BAHAN |
|
|
|
|
|
Marmer |
Bh |
3,1000 |
100.359,71 |
311.115,11 |
|
Semen Portland |
Kg |
8,1900 |
1.250,00 |
10.237,50 |
|
Pasir Pasang |
M3 |
0,0450 |
350.000,00 |
15.750,00 |
|
Semen warna |
Kg |
0,6500 |
5.000,00 |
3.250,00 |
|
Paku 12cm |
Bh |
3,0300 |
23.000,00 |
69.690,00 |
|
|
|
JUMLAH HARGA BAHAN |
410.042,61 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
592.627,61 |
E |
Overhead & Profit |
10% x D |
|
|
59.262,76 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
651.890,37 |