A.4.4.3.9b - Pemasangan 1 M2 lantai ubin granit unpolished ukuran 30cm x 60cm
A.4.4.3.9b - Pemasangan 1 M2 lantai ubin granit unpolished ukuran 30cm x 60cm |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,2500 |
81.500,00 |
20.375,00 |
|
Tukang Batu |
OH |
0,1250 |
96.500,00 |
12.062,50 |
|
Kepala tukang |
OH |
0,0130 |
107.000,00 |
1.391,00 |
|
Mandor |
OH |
0,0130 |
107.000,00 |
1.391,00 |
|
|
|
JUMLAH HARGA TENAGA |
35.219,50 |
B |
BAHAN |
|
|
|
|
|
Ubin granit unpolished |
Bh |
5,9360 |
37.769,78 |
224.201,44 |
|
Semen Portland |
Kg |
9,8000 |
1.250,00 |
12.250,00 |
|
Semen warna |
Kg |
1,3000 |
5.000,00 |
6.500,00 |
|
Pasir pasang |
M3 |
0,0450 |
350.000,00 |
15.750,00 |
|
|
|
JUMLAH HARGA BAHAN |
258.701,44 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
293.920,94 |
E |
Overhead & Profit |
10% x D |
|
|
29.392,09 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
323.313,03 |