A.4.5.2.1 - Pemasangan 1 M2 atap genteng palentong kecil

A.4.5.2.1 - Pemasangan 1 M2 atap genteng palentong kecil
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,1500 81.500,00 12.225,00
Tukang Kayu OH 0,0750 96.500,00 7.237,50
Kepala tukang OH 0,0075 107.000,00 802,50
Mandor OH 0,0080 107.000,00 856,00
JUMLAH HARGA TENAGA 21.121,00
B BAHAN
Genteng palentong Bh 25,0000 2.000,00 50.000,00
JUMLAH HARGA BAHAN 50.000,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 71.121,00
E Overhead & Profit 10% x D 7.112,10
F HARGA SATUAN   PEKERJAAN ( D + E )    78.233,10