Skip to content Skip to sidebar Skip to footer

A.4.5.2.10a - Pemasangan 1 M2 atap asbes gelombang 180 cm X 105 cm X 5 mm

A.4.5.2.10a - Pemasangan 1 M2 atap asbes gelombang 180 cm X 105   cm X 5 mm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,1400 81.500,00 11.410,00
Tukang Kayu OH 0,0700 96.500,00 6.755,00
Kepala tukang OH 0,0070 107.000,00 749,00
Mandor OH 0,0070 107.000,00 749,00
JUMLAH HARGA TENAGA 19.663,00
B BAHAN
Asbes gel 180 x 105 Lbr 0,5500 50.000,00 27.500,00
Paku pancing 6x23 Kg 0,1200 25.000,00 3.000,00
JUMLAH HARGA BAHAN 30.500,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 50.163,00
E Overhead & Profit 10% x D 5.016,30
F HARGA SATUAN   PEKERJAAN ( D + E )    55.179,30



======= ARTIKEL TERKAIT =======



Post a Comment for "A.4.5.2.10a - Pemasangan 1 M2 atap asbes gelombang 180 cm X 105 cm X 5 mm"