Skip to content Skip to sidebar Skip to footer

A.4.5.2.13a - Pemasangan 1 M2 atap asbes gelombang 210 cm X 80 cm X 4 mm

A.4.5.2.13a - Pemasangan 1 M2 atap asbes gelombang 210 cm X 80   cm X 4 mm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,1400 81.500,00 11.410,00
Tukang Kayu OH 0,0700 96.500,00 6.755,00
Kepala tukang OH 0,0070 107.000,00 749,00
Mandor OH 0,0070 107.000,00 749,00
JUMLAH HARGA TENAGA 19.663,00
B BAHAN
Asbes gel 210   x 80 cm Lbr 0,6000 40.000,00 24.000,00
Paku pancing 6x23 Kg 0,1200 25.000,00 3.000,00
JUMLAH HARGA BAHAN 27.000,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 46.663,00
E Overhead & Profit 10% x D 4.666,30
F HARGA SATUAN   PEKERJAAN ( D + E )    51.329,30