A.4.5.2.32 - Pemasangan 1 M2 genteng metal
A.4.5.2.32 - Pemasangan 1 M2 genteng metal | |||||
---|---|---|---|---|---|
NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
A | TENAGA | ||||
Pekerja | OH | 0,2000 | 81.500,00 | 16.300,00 | |
Tukang Kayu | OH | 0,1000 | 96.500,00 | 9.650,00 | |
Kepala tukang | OH | 0,0100 | 107.000,00 | 1.070,00 | |
Mandor | OH | 0,0010 | 107.000,00 | 107,00 | |
JUMLAH HARGA TENAGA | 27.127,00 | ||||
B | BAHAN | ||||
Genteng metal | Bh | 1,0200 | 65.625,00 | 66.937,50 | |
Paku biasa ½”-1” | Kg | 0,2000 | 23.600,00 | 4.720,00 | |
JUMLAH HARGA BAHAN | 71.657,50 | ||||
C | ALAT | ||||
- | - | - | - | - | |
JUMLAH HARGA ALAT | - | ||||
D | Jumlah | (A+B+C) | 98.784,50 | ||
E | Overhead & Profit | 10% x D | 9.878,45 | ||
F | HARGA SATUAN PEKERJAAN | ( D + E ) | 108.662,95 |