A.4.5.2.34 - Pemasangan 1 M' nok genteng beton
A.4.5.2.34 - Pemasangan 1 M' nok genteng beton | |||||
---|---|---|---|---|---|
NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
A | TENAGA | ||||
Pekerja | OH | 0,4000 | 81.500,00 | 32.600,00 | |
Tukang Kayu | OH | 0,2000 | 96.500,00 | 19.300,00 | |
Kepala tukang | OH | 0,0200 | 107.000,00 | 2.140,00 | |
Mandor | OH | 0,0200 | 107.000,00 | 2.140,00 | |
JUMLAH HARGA TENAGA | 56.180,00 | ||||
B | BAHAN | ||||
Nok genteng beton | Bh | 3,5000 | 12.000,00 | 42.000,00 | |
Paku biasa ½”-1” | Kg | 0,0500 | 23.600,00 | 1.180,00 | |
Semen PC | Kg | 10,8000 | 1.250,00 | 13.500,00 | |
Pasir pasang | M3 | 0,0320 | 350.000,00 | 11.200,00 | |
Semen warna | Kg | 1,0000 | 5.000,00 | 5.000,00 | |
JUMLAH HARGA BAHAN | 72.880,00 | ||||
C | ALAT | ||||
- | - | - | - | - | |
JUMLAH HARGA ALAT | - | ||||
D | Jumlah | (A+B+C) | 129.060,00 | ||
E | Overhead & Profit | 10% x D | 12.906,00 | ||
F | HARGA SATUAN PEKERJAAN | ( D + E ) | 141.966,00 |