A.4.5.2.38a - Pemasangan 1 M2 atap seng gelombang

A.4.5.2.38a - Pemasangan 1 M2 atap seng   gelombang
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,1200 81.500,00 9.780,00
Tukang Kayu OH 0,0600 96.500,00 5.790,00
Kepala tukang OH 0,0060 107.000,00 642,00
Mandor OH 0,0060 107.000,00 642,00
JUMLAH HARGA TENAGA 16.854,00
B BAHAN
Seng gel 3”x6” Lbr 0,7000 72.000,00 50.400,00
Paku biasa ½”-1” Kg 0,0200 23.600,00 472,00
JUMLAH HARGA BAHAN 50.872,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 67.726,00
E Overhead & Profit 10% x D 6.772,60
F HARGA SATUAN   PEKERJAAN ( D + E )    74.498,60