A.4.5.2.38b - Pemasangan 1 M2 atap Zingcalum tebal 0.5 mm

A.4.5.2.38b - Pemasangan 1 M2 atap Zingcalum   tebal 0.5 mm
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,1200 81.500,00 9.780,00
Tukang Kayu OH 0,0600 96.500,00 5.790,00
Kepala tukang OH 0,0060 107.000,00 642,00
Mandor OH 0,0060 107.000,00 642,00
JUMLAH HARGA TENAGA 16.854,00
B BAHAN
Zingcalum Lbr 1,0500 55.000,00 57.750,00
Paku biasa ½”-1” Kg 0,0200 23.600,00 472,00
JUMLAH HARGA BAHAN 58.222,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 75.076,00
E Overhead & Profit 10% x D 7.507,60
F HARGA SATUAN   PEKERJAAN ( D + E )    82.583,60