A.4.5.2.39 - Pemasangan 1 M' nok atap seng

A.4.5.2.39 - Pemasangan 1 M'nok atap seng
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,1500 81.500,00 12.225,00
Tukang Kayu OH 0,0700 96.500,00 6.755,00
Kepala tukang OH 0,0070 107.000,00 749,00
Mandor OH 0,0060 107.000,00 642,00
JUMLAH HARGA TENAGA 20.371,00
B BAHAN
Seng plat 3”x6”bjls30 Lbr 0,3000 41.000,00 12.300,00
Paku biasa ½”-1” Kg 0,0400 23.600,00 944,00
JUMLAH HARGA BAHAN 13.244,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 33.615,00
E Overhead & Profit 10% x D 3.361,50
F HARGA SATUAN   PEKERJAAN ( D + E )    36.976,50