A.4.5.2.42 - Pemasangan 1 M2 alumunium foil/sisalation

A.4.5.2.42 - Pemasangan 1 M2 alumunium   foil/sisalation
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,1500 81.500,00 12.225,00
Tukang Kayu OH 0,0500 96.500,00 4.825,00
Kepala tukang OH 0,0050 107.000,00 535,00
Mandor OH 0,0080 107.000,00 856,00
JUMLAH HARGA TENAGA 18.441,00
B BAHAN
Alumunium foil M2 1,0500 4.500,00 4.725,00
JUMLAH HARGA BAHAN 4.725,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 23.166,00
E Overhead & Profit 10% x D 2.316,60
F HARGA SATUAN   PEKERJAAN ( D + E )    25.482,60