A.4.6.1.13 - Pemasangan 1 M3 konstruksi kuda-kuda konvensional, kayu kelas II bentang 6 meter
A.4.6.1.13 - Pemasangan 1 M3 konstruksi kuda-kuda konvensional, kayu kelas II bentang 6 meter |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
4,0000 |
81.500,00 |
326.000,00 |
|
Tukang kayu |
OH |
12,0000 |
96.500,00 |
1.158.000,00 |
|
Kepala tukang |
OH |
1,2000 |
107.000,00 |
128.400,00 |
|
Mandor |
OH |
0,2000 |
107.000,00 |
21.400,00 |
|
|
|
JUMLAH HARGA TENAGA |
1.633.800,00 |
B |
BAHAN |
|
|
|
|
|
Balok kayu |
M3 |
1,1000 |
7.500.000,00 |
8.250.000,00 |
|
Besi strip tebal 5mm |
Kg |
15,0000 |
12.000,00 |
180.000,00 |
|
Paku 12 cm |
Kg |
5,6000 |
23.000,00 |
128.800,00 |
|
|
|
JUMLAH HARGA BAHAN |
8.558.800,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
10.192.600,00 |
E |
Overhead & Profit |
10% x D |
|
|
1.019.260,00 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
11.211.860,00 |