A.4.6.1.14 - Pemasangan 1 M3 konstruksi kuda-kuda expose, kayu kelas I

A.4.6.1.14 - Pemasangan 1 M3 konstruksi kuda-kuda expose, kayu   kelas I
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 6,7000 81.500,00 546.050,00
Tukang kayu OH 20,1000 96.500,00 1.939.650,00
Kepala tukang OH 2,0100 107.000,00 215.070,00
Mandor OH 0,3350 107.000,00 35.845,00
JUMLAH HARGA TENAGA 2.736.615,00
B BAHAN
Balok kayu M3 1,2000 29.200.000,00 35.040.000,00
Besi strip tebal 5mm Kg 15,0000 12.000,00 180.000,00
Paku 12 cm Kg 5,6000 23.000,00 128.800,00
JUMLAH HARGA BAHAN 35.348.800,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 38.085.415,00
E Overhead & Profit 10% x D 3.808.541,50
F HARGA SATUAN   PEKERJAAN ( D + E ) 41.893.956,50