Skip to content
A.4.6.1.14 - Pemasangan 1 M3 konstruksi kuda-kuda expose, kayu kelas I
A.4.6.1.14 - Pemasangan 1 M3 konstruksi kuda-kuda expose, kayu kelas I |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
6,7000 |
81.500,00 |
546.050,00 |
|
Tukang kayu |
OH |
20,1000 |
96.500,00 |
1.939.650,00 |
|
Kepala tukang |
OH |
2,0100 |
107.000,00 |
215.070,00 |
|
Mandor |
OH |
0,3350 |
107.000,00 |
35.845,00 |
|
|
|
JUMLAH HARGA TENAGA |
2.736.615,00 |
B |
BAHAN |
|
|
|
|
|
Balok kayu |
M3 |
1,2000 |
29.200.000,00 |
35.040.000,00 |
|
Besi strip tebal 5mm |
Kg |
15,0000 |
12.000,00 |
180.000,00 |
|
Paku 12 cm |
Kg |
5,6000 |
23.000,00 |
128.800,00 |
|
|
|
JUMLAH HARGA BAHAN |
35.348.800,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
38.085.415,00 |
E |
Overhead & Profit |
10% x D |
|
|
3.808.541,50 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
41.893.956,50 |