A.4.6.1.15 - Pemasangan 1 M3 konstruksi gordeng, kayu kelas II (kamfer)
A.4.6.1.15 - Pemasangan 1 M3 konstruksi gordeng, kayu kelas II (kamfer)
A.4.6.1.15 - Pemasangan 1 M3 konstruksi gordeng, kayu kelas II (kamfer) |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
6,7000 |
81.500,00 |
546.050,00 |
|
Tukang kayu |
OH |
20,1000 |
96.500,00 |
1.939.650,00 |
|
Kepala tukang |
OH |
2,0100 |
107.000,00 |
215.070,00 |
|
Mandor |
OH |
0,3350 |
107.000,00 |
35.845,00 |
|
|
|
JUMLAH HARGA TENAGA |
2.736.615,00 |
B |
BAHAN |
|
|
|
|
|
Balok kayu |
M3 |
1,1000 |
7.500.000,00 |
8.250.000,00 |
|
Besi strip tebal 5 mm |
Kg |
15,0000 |
12.000,00 |
180.000,00 |
|
Paku 12 cm |
Kg |
3,0000 |
23.000,00 |
69.000,00 |
|
|
|
JUMLAH HARGA BAHAN |
8.499.000,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
11.235.615,00 |
E |
Overhead & Profit |
10% x D |
|
|
1.123.561,50 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
12.359.176,50 |