A.4.6.2.12 - Pemasangan 1 Buah Door holder
A.4.6.2.12 - Pemasangan 1 Buah Door holder | |||||
---|---|---|---|---|---|
NO | URAIAN | SATUAN | KOEFISIEN | HARGA SATUAN | JUMLAH HARGA |
A | TENAGA | ||||
Pekerja | OH | 0,0500 | 81.500,00 | 4.075,00 | |
Tukang kayu | OH | 0,5000 | 96.500,00 | 48.250,00 | |
Kepala tukang | OH | 0,0500 | 107.000,00 | 5.350,00 | |
Mandor | OH | 0,0030 | 107.000,00 | 321,00 | |
JUMLAH HARGA TENAGA | 57.996,00 | ||||
B | BAHAN | ||||
Door holder | Bh | 1,0000 | 80.000,00 | 80.000,00 | |
JUMLAH HARGA BAHAN | 80.000,00 | ||||
C | ALAT | ||||
- | - | - | - | - | |
JUMLAH HARGA ALAT | - | ||||
D | Jumlah | (A+B+C) | 137.996,00 | ||
E | Overhead & Profit | 10% x D | 13.799,60 | ||
F | HARGA SATUAN PEKERJAAN | ( D + E ) | 151.795,60 |