A.4.6.2.13.a - Pemasangan 1 Buah Gerendel

A.4.6.2.13.a - Pemasangan 1 Buah Gerendel
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0100 81.500,00 815,00
Tukang kayu OH 0,1000 96.500,00 9.650,00
Kepala tukang OH 0,0100 107.000,00 1.070,00
Mandor OH 0,0050 107.000,00 535,00
JUMLAH HARGA TENAGA 12.070,00
B BAHAN
Gerendel Bh 1,0000 10.000,00 10.000,00
JUMLAH HARGA BAHAN 10.000,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 22.070,00
E Overhead & Profit 10% x D 2.207,00
F HARGA SATUAN   PEKERJAAN ( D + E )    24.277,00