A.4.6.2.16 - Pemasangan 1 M2 kaca tebal 3 mm
A.4.6.2.16 - Pemasangan 1 M2 kaca tebal 3 mm |
NO |
URAIAN |
SATUAN |
KOEFISIEN |
HARGA SATUAN |
JUMLAH HARGA |
A |
TENAGA |
|
|
|
|
|
Pekerja |
OH |
0,0150 |
81.500,00 |
1.222,50 |
|
Tukang kayu |
|
0,1500 |
96.500,00 |
14.475,00 |
|
Kepala tukang |
|
0,0150 |
107.000,00 |
1.605,00 |
|
Mandor |
OH |
0,0008 |
107.000,00 |
85,60 |
|
|
|
JUMLAH HARGA TENAGA |
17.388,10 |
B |
BAHAN |
|
|
|
|
|
Kaca tebal 3mm |
M2 |
1,1000 |
110.000,00 |
121.000,00 |
|
Sealant |
Kg |
0,0500 |
30.000,00 |
1.500,00 |
|
|
|
JUMLAH HARGA BAHAN |
122.500,00 |
C |
ALAT |
|
|
|
|
|
- |
- |
- |
- |
- |
|
|
|
JUMLAH HARGA ALAT |
- |
D |
Jumlah |
(A+B+C) |
|
|
139.888,10 |
E |
Overhead & Profit |
10% x D |
|
|
13.988,81 |
F |
HARGA SATUAN PEKERJAAN |
( D + E ) |
|
|
153.876,91 |