A.4.6.2.4 - Pemasangan 1 Buah kunci silinder

A.4.6.2.4 - Pemasangan 1 Buah kunci silinder
NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0050 81.500,00 407,50
Tukang kayu OH 0,5000 96.500,00 48.250,00
Kepala tukang OH 0,0500 107.000,00 5.350,00
Mandor OH 0,0030 107.000,00 321,00
JUMLAH HARGA TENAGA 54.328,50
B BAHAN
Kunci silinder Bh 1,0000 250.000,00 250.000,00
JUMLAH HARGA BAHAN 250.000,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 304.328,50
E Overhead & Profit 10% x D 30.432,85
F HARGA SATUAN   PEKERJAAN ( D + E )    334.761,35