NO URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
A TENAGA
Pekerja OH 0,0150 81.500,00 1.222,50
Tukang kayu OH 0,1500 96.500,00 14.475,00
Kepala tukang OH 0,0150 107.000,00 1.605,00
Mandor OH 0,0008 107.000,00 85,60
JUMLAH HARGA TENAGA 17.388,10
B BAHAN
Engsel pintu Bh 1,0000 60.000,00 60.000,00
JUMLAH HARGA BAHAN 60.000,00
C ALAT
- - - - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 77.388,10
E Overhead & Profit 10% x D 7.738,81
F HARGA SATUAN   PEKERJAAN ( D + E )    85.126,91